 AT3600 High Voltage Transformer Tester
Superior by design, the AT3600, with its patented digital measurement techniques, has revolutionized transformer testing throughout out the world. Only the AT3600 combines high and low voltage testing in one station to provide this combination of speed, accuracy, flexibility and reliability.
AT3600  From $18,360.00 Help
High Voltage Transformer Tester
Estimated Lead Time: 56 days Help
Add to Cart
AT3600 Demonstation
Rep and Self -Demo Systems Available
Estimated Lead Time: 22 days
Request

Need a rental? Click here for information.

Tests: DCRT - DC Hi-Pot Ramp   Back To Tests

Price: $2,145.00
Add to Cart

Where Used

Hi-Pot Ramp testing (to check for insulation breakdown between windings or between windings and the screen or core) is often specified for power line transformers or for switched mode power transformers in applications where safety is important.

It is typically performed between all primary windings connected together, and all secondary windings plus the screen connected together.

DCRT Diagram

Specifying the Measurement

During the test, a dc target voltage is applied across two groups of windings with the windings in each group being shorted together. The voltage and current are monitored throughout the ramp time.

In programming the tester you may select the voltage (from 100V to 7KVdc), the current trip level (1mA to 3mA), and the ramp up times (1 to 2sec), all to suit the specification of the transformer under test.

The purpose is to check the safety isolation between windings, windings and core, or windings and screens, measuring the voltage at which a user specified current is exceeded, by ramping to a maximum user specified voltage at a user specified frequency.

The operation is to ramp up the test voltage while measuring the voltage across the selected terminals and continually monitor the current to check it is below the test limit.

If target voltage is reached before and the maximum monitored current is met the test has "Passed".

If the maximum monitored current is met before the target voltage is reached the test has "Failed".

Details
Overview
Benefits
Cost Savings
Tests
Fixturing
Applications
What's In the Box?
Software
 
More Information
Brochure
User Manual
Technical Articles

© 2006-2009 Voltech Instruments, Inc.   Terms and conditions | Terms of use | Privacy statement | About Voltech | Contact webmaster | Website help | Contact us
Credit card processing